Scrum - All MCQs

Basic, Scrum Product Backlog

1. Which is not an event in sprint?

A. Sprint Planning

B. Sprint Review

C. Daily Standup

D. Spring Closure

Answer: D

2. An order of the Product Backlog Items should be based on ____ ?

A. Value and Risk

B. Work Estimates and Available expertise

C. dependencies

D. All of above

Answer: D

3. What is the purpose of scrum sprint planning meeting?

A. It setups planning for the entire team for success

B. To improve communication and identify impediments to development

C. To show the customers and stakeholders the work they have accomplished

D. All of above

Answer: A

4. What are the questions for daily standup meeting?

A. What did you do yesterday?

B. What will you do today?

C. Are there any impediments in your way?

D. All of above

Answer: D

5. What are the questions for daily standup meeting?

A. What did you do yesterday?

B. What will you do today?

C. Are there any impediments in your way?

D. All of above

Answer: D

6. When does the scrum sprint planning meeting start ?

A. At the end of sprint

B. Once per a day

C. At the beginning of the sprint

D. None of above

Answer: C

7. Who are the attendees of scrum daily stand up meeting?

A. Development Team

B. Scrum Master

C. Product Owner

D. All of above

Answer: D

8. What is the best way to create Product Backlog Items?

A. a collaborative and iterative approach with Development team

B. a collaborative and iterative approach with whole scrum team

C. a collaborative and iterative approach with Product Owner

D. None of above

Answer: B

9. A BurnDown chart is used to display ____ ?

A. The velocity of the team

B. Amount of the remaining work with time respect

C. The number capacity of the team

D. All of above

Answer: B

10. What is the duration of daily standup meeting?

A. 15 Minutes

B. 5 Minutes

C. 10 Minutes

D. 1 hour

Answer: A